Tendr - rekonstrukce úpravny vody
Czech Republic Prague: ISPA - reconstruction of drinking water supply system,
construction of sewerage system, reconstruction of waterreatment and waste water
treatment plants in the region Podkrusnohori Stav tendru: avízo tendru Banka:
Evropská unie - program ISPA Klíčová slova: ISPA , potrubí , stavební práce ,
úpravny vody Popis: Částečná rekonstrukce úpravny vody a výměna porubí na pitnou
vodu 2002/S 95-074533 Group of measures No 1 - drinking water Podkrusnohorí,
region Ústecky, NUTS II - north-west, Czech Republic 1. Publication reference:
EuropeAid/114038/D/SV/CZ 2. Procedure: Open. 3. Programme: ISPA - environment.
4. Financing: Financing memorandum for ISPA measure No 2001/CZ/16/P/PE/004 -
budgetary line B7-020, Czech State environmental fund, budget of the contracting
authority (SVS). 5. Contracting authority: Implementing Agency - State
Environmental Fund of the Czech Republic, Prague, Czech Republic. 6. Contract
description: The proposed works should be made for a group of eight individual
measures within the whole project. The group of measures No 1 consists of the
two following sub-projects: P0109- partial reconstruction and modernization of
water treatment plant Hradiste (built 1970-1976; existing capacity 1 050
litres/s); the recontruction shall be executed concurrently with running water
treatment process; P0111 - replacement of existing steel drinking water main DN
600 Zelenice - Bílina by new pipeline DN 500 (non ferrous material) - section ca
6,2 km. 7. Indicative number and titles of lots: Single lot. 8. Intended timing
of publication: June 2002. 9. Additional information: None. 10. Legal basis:
Council Regulation (EC) No 1267/1999 of 21 June 1999 establishing an Instrument
for Structural Policies for Pre-accession. Remarks: There must be a minimum
period of 30 calendar days between the publication of this contract forecast and
the publication of the corresponding procurement notice. No applications or
requests for further information should be sent at this stage. publikováno:
20.05.2002
Czech Republic
Prague: ISPA - reconstruction of drinking water supply system, construction of sewerage system, reconstruction of waterreatment and waste water treatment plants in the region Podkrusnohori
Stav tendru: avízo tendru
Banka: Evropská unie - program ISPA
Klíčová slova: ISPA ,
potrubí ,
stavební práce ,
úpravny vody
Popis:
Částečná rekonstrukce úpravny vody a výměna porubí na pitnou vodu
2002/S 95-074533
Group of measures No 1 - drinking water
Podkrusnohorí, region Ústecky, NUTS II - north-west, Czech Republic
1.
Publication reference: EuropeAid/114038/D/SV/CZ
2.
Procedure: Open.
3.
Programme: ISPA - environment.
4.
Financing: Financing memorandum for ISPA measure No 2001/CZ/16/P/PE/004 - budgetary line B7-020, Czech State environmental fund, budget of the contracting authority (SVS).
5.
Contracting authority: Implementing Agency - State Environmental Fund of the Czech Republic, Prague, Czech Republic.
6.
Contract description: The proposed works should be made for a group of eight individual measures within the whole project. The group of measures No 1 consists of the two following sub-projects: P0109- partial reconstruction and modernization of water treatment plant Hradiste (built 1970-1976; existing capacity 1 050 litres/s); the recontruction shall be executed concurrently with running water treatment process; P0111 - replacement of existing steel drinking water main DN 600 Zelenice - Bílina by new pipeline DN 500 (non ferrous material) - section ca 6,2 km.
7.
Indicative number and titles of lots: Single lot.
8.
Intended timing of publication: June 2002.
9.
Additional information: None.
10.
Legal basis: Council Regulation (EC) No 1267/1999 of 21 June 1999 establishing an Instrument for Structural Policies for
Pre-accession.
Remarks:
There must be a minimum period of 30 calendar days between the publication of this contract forecast and the publication of the
corresponding procurement notice.
No applications or requests for further information should be sent at this stage.